Carleton Washburne School
The diagrams above are conceptual and represent ideas developed during the Master Plan. They do not represent a design process or actual orientation of additions or renovations. Graphics are for illustrative purposes only. Here’s how to navigate this interactive graphic:
- Use the arrows in the TOP RIGHT corner of the image to toggle between floors.
- Click on each number in the images for Floors 1, 2, and 3 for more information about EMFP elements.
Identified Long-Range Needs
Building Needs
Baseline
$15,805,171
Renovations
$24,975,000
First Floor:
Classroom Wing Renovations
Cafeteria Renovation
Maker Space Renovations
Locker Room Renovations
Renovate Chorus for Resource
Upgrade Resource Rooms
Renovate Industrial Arts for STEM
Second Floor:
Classroom Wing Renovations
Convert Resource Center to Classroom Wing
Relocate Resource Center
Third Floor:
Reconfigure Classrooms
Renovate Broadcast Studio
Expansion/Additions
$19,989,773
Kitchen Expansion
Classroom Wing Expansions
Kinetic Wellness Addition
Locker Room Expansions
Infill Courtyards
Resource Center Addition
Green Roofs
Site Needs
Site Circulation + Parking
$562,500
Expand Staff Parking Lot
Reconfigure Drop-Off
Storm Water Detention
*The above items are listed with the Order Of Magnitude Cost Estimate (OME) and site work allowance associated with the work.